Fig 1. Lay a normal 10mm bed of mortar. Use trowel to cut back mortar approximately 15mm from the face of the Tilebrick unit.
Do not put up multiple course corners first |
| |
|
|
Fig 2. The vertical perpend joints are tapered and therefore only need to be buttered from the rear covering approximately 2/3rds of the end. |
| |
|
|
Fig 3. The Tilebrick units should be spaced approximately 1mm - 3mm apart at the front face with no mortar visible.
*2/3rds mortar coverage as shown in Fig 2. |
| |
|
|
Fig 4. Lay one course at a time and lay the string line to the front edge of the brick. Check cross-levels frequently to prevent tilting. |
| |
|
|
Fig 5. Use a designation (iii) mix and a well-graded building sand. |
| |
|
|
Fig 6. Lead with the outer skin of Tilebrick (if insulation type allows) to ensure vertical joints are well filled on the rear face. |